The Transmission Company of Nigeria, TCN said, it will ration power supply to parts of the Federal Capital Territory beginning from 6th to 20th January, 2024.

The development follows the Federal Capital Development Authority’s (FCDA) road dualisation project along the Apo axis.

Change of Name

The TCN’s General Manager in charge of Public Affairs, Mrs Ndidi Mbah, said on Saturday that the project requires the relocation of eight 132kV and 33kV towers along the Kukwaba/Apo 132kV line, which will result in power outage from 9am to 4pm daily, affecting areas such as Kubwa, Karu, Maraba, Nyanya, Masaka, Keffi, Kukwaba, and Apo Mechanic.

Other areas to be affected include parts of Lugbe, Trademore Estate, Pyakasa, Sabon Lugbe Chika, and Alaita axis.
TCN apologises for the inconvenience and assures customers that power supply will be restored as soon as the towers relocation and cable stringing are completed.

”This relocation work will necessitate a planned power outage from 6th to 20th Jan from 9am to 4 pm daily, which is the estimated duration for the dismantling and construction of the towers.

“It will also allow for the restringing of the power cables that will enable resumption of bulk power supply to the Apo Transmission Substation from Gwagwalada Substation.

”While the relocation of the transmission towers is a necessity for the road completion project, TCN apologises for the inconvenience this planned power outage will cause,” she said.

10 / 100

Contact Us:

  • Address: Address: 1st Floor,  Nwakpabi Plaza,  Suite 110, Waziri Ibrahim Crescent, Apo,  Abuja
  • Tel: +234 7036084449, +234 8066722600, +234 7012711701
  • Email: info@capitalpost.ng
  • Email: capitalpost20@gmail.com

Quick Links: